SpaceX to Dismantle Unpermitted Gas Turbines in Memphis Within Year, Transition to 1.2 GW Permanent Plant
SpaceX will dismantle unpermitted natural gas turbines in Memphis within a year, transitioning to a 1.2 GW permanent gas-fired power plant. The temporary turbines, which power xAI's Colossus data center, will be fully removed by July 2027. There are 69 turbines currently operating. The unpermitted units have sparked environmental lawsuits from the NAACP and the Southern Environmental Law Center. SpaceX acquired xAI in February 2026 and plans to purchase $2.8 billion in gas turbines for data centers over three years.
SpaceX announced it will gradually dismantle natural gas turbines mounted on trailers in Memphis within a year. These turbines had been powering xAI's Colossus data center. According to the plan released by SpaceX, the company will transition to a permanent 1.2-gigawatt natural gas power plant, but the temporary turbines will not be fully removed until July 2027. A total of 69 natural gas turbines are currently in operation, many of which have been running for several months.
The unpermitted turbines have sparked environmental controversy. The NAACP and the Southern Environmental Law Center had previously filed a lawsuit against xAI. SpaceX completed its acquisition of xAI in February 2026. In its initial public offering filing, SpaceX disclosed plans to purchase $2.8 billion worth of natural gas turbines for its data centers over the next three years.
SpaceX argues that because the existing turbines have remained on transport truck trailers, they do not require operating permits. However, US federal regulations clearly state that the size and purpose of these units determine that they must obtain the appropriate permits regardless of the carrier on which they are mounted. The turbines are located in southern Mississippi, near the Tennessee border, an area that is among the most polluted in the country.
Last month, the US Department of Justice sided with SpaceX in the lawsuit brought by the NAACP, claiming that the unpermitted turbines involve matters of "national, economic, and energy security." According to permits issued by the state of Mississippi, the new power plant under construction by SpaceX consists of 41 natural gas turbines with individual capacities ranging from 16.48 megawatts to 50 megawatts, a different model from the 69 turbines currently in operation.
Why this event matters
The event has a measured impact on 2 industrys. The strongest current signal is positive for Thermal Power, with intensity 50/100 and 70% confidence over a medium term horizon.
Thermal Power
- Direction
- positive
- Intensity
- 50
- Confidence
- 70%
- Horizon
- Medium term
Artificial Intelligence
- Direction
- mixed
- Intensity
- 40
- Confidence
- 60%
- Horizon
- Short term
Impact figures are analytical estimates that combine direction, intensity, confidence and event importance. They are not investment advice.